Project Completion Certificate (Ground Water)
Scheme ID: 20015880 Name of Scheme: Barnai No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 3340 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 19-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 22.5/85.31 BARNAI 27.87082 79.96901
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump - 1 43.2 M3 / 41 M BARNAI 27.87082 79.96901
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT - 1 225 KL - 12 M BARNAI 27.87015 79.96929
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI - K 7 150 0.028
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / 6Kg 63 4.239
2 HDPE / 6Kg 75 0.465
3 HDPE / 6Kg 90 1.125
4 HDPE / 6Kg 110 0.192
5 HDPE / 6Kg 140 1.238
6 HDPE / 6Kg 160 0.180
HSC Connection
Sno. Total Nos.
1 619
Other Details
2.27
0.00
2.27
18-Jun-2024
06-Dec-2024