Project Completion Certificate (Ground Water)
Scheme ID: 20016644 Name of Scheme: HTWA GOPAL PAYAGPUR PWS No. of Villages: 1 No. of Habitation Covered: 4
Total Population Covered: 3817 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2025 Actual Date of Completion (Capex): 09-Nov-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24.08/176.03 HTWA GOPAL 27.442862 81.788172
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump 30/35 HTWA GOPAL 27.442862 81.788172
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/12 HTWA GOPAL 27.442908 81.788141
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 RISING MAIN/DI-K7 150 0.0255
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6; Class PE-100 63 10.44
2 HDPE Pipe PN-6; Class PE-100 75 0.942
3 HDPE Pipe PN-6; Class PE-100 90 0.973
4 HDPE Pipe PN-6; Class PE-100 110 0.423
5 HDPE Pipe PN-6; Class PE-100 125 0.514
6 HDPE Pipe PN-6; Class PE-100 160 0.866
HSC Connection
Sno. Total Nos.
1 310
Other Details
2.06
1.87
1.83
01-May-2024
10-Nov-2025