| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20017854 | Name of Scheme: Chaudhariyapur | No. of Villages: 2 | No. of Habitation Covered: 3 |
| Total Population Covered: 3370 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 26-Jul-2023 | Actual Date of Completion (Capex): 11-Jun-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 25.04M/ 122.77M | Chaudhariyapur | 27.263987 | 80.958563 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 0.800 M³ per Min /45Mtr | Chaudhariyapur | 27.263987 | 80.958563 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 225KL/ 16 Mtr | Chaudhariyapur | 27.264096 | 80.958615 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D. I. Pipe | 150 | 0.02132 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6, Class PE-100 | 63 | 2.8698 | |
| 2 | HDPE Pipe PN-6, Class PE-100 | 75 | 3.2642 | |
| 3 | HDPE Pipe PN-6, Class PE-100 | 90 | 1.1052 | |
| 4 | HDPE Pipe PN-6, Class PE-100 | 110 | 0.866 | |
| 5 | HDPE Pipe PN-6, Class PE-100 | 125 | 0.544 | |
| 6 | HDPE Pipe PN-6, Class PE-100 | 160 | 0.6379 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 335 |