Project Completion Certificate (Ground Water)
Scheme ID: 20017959 Name of Scheme: KARNAI JARWAL PWS No. of Villages: 1 No. of Habitation Covered: 12
Total Population Covered: 3538 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2025 Actual Date of Completion (Capex): 25-Jul-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24.1/259.98 KARNAI 27.144582 81.588441
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump 27/35 KARNAI 27.144582 81.588441
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/12 KARNAI 27.144429 81.58796
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 RISING MAIN/DI-K7 125 0.038
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6; Class PE-100 63 7.351
2 HDPE Pipe PN-6; Class PE-100 90 1.259
3 HDPE Pipe PN-6; Class PE-100 140 1.175
HSC Connection
Sno. Total Nos.
1 267
Other Details
1.71
0.00
1.75
25-Jul-2025
26-Jul-2025