Project Completion Certificate (Ground Water)
Scheme ID: 20018064 Name of Scheme: Natani No. of Villages: 3 No. of Habitation Covered: 4
Total Population Covered: 2710 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 02-May-2023 Actual Date of Completion (Capex): 28-Mar-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 18.02/126.04 Natani 26.6285 83.2099
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 36/43 Natani 26.6285 83.2099
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 175/16 Natani 26.6285 83.2099
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.030 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.009 Laying Completed
2 HDPE 75 0.494 Laying Completed
3 HDPE 90 1.934 Laying Completed
4 HDPE 110 0.108 Laying Completed
5 HDPE 140 0.676 Laying Completed
6 HDPE 160 0.482 Laying Completed
HSC Connection
Sno. Total Nos.
1 260
Other Details
2.14
0.00
2.13
31-Mar-2026
01-Apr-2026