Project Completion Certificate (Ground Water)
Scheme ID: 20019517 Name of Scheme: MANIKPAR No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2909 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 27-Feb-2023 Actual Date of Completion (Capex): 10-May-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 165 Manikpar 26.476813 83.124959
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submercible Pump 700 LPM/ 46 m Manikpar 26.476813 83.124959
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 ESR 200 KL/ 18m Manikpar 26.476813 83.124959
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 150 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.036
2 HDPE 75 0.06
3 HDPE 90 0.706
4 HDPE 110 0.885
5 HDPE 125 0.535
6 HDPE 140 0.886
7 HDPE 160 0.537
HSC Connection
Sno. Total Nos.
1 489
Other Details
2.65
0.00
2.65
10-Aug-2023
19-Nov-2024