| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20019517 | Name of Scheme: MANIKPAR | No. of Villages: 3 | No. of Habitation Covered: 3 |
| Total Population Covered: 2909 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 27-Feb-2023 | Actual Date of Completion (Capex): 10-May-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 165 | Manikpar | 26.476813 | 83.124959 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submercible Pump | 700 LPM/ 46 m | Manikpar | 26.476813 | 83.124959 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | ESR | 200 KL/ 18m | Manikpar | 26.476813 | 83.124959 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. | 150 | 0.035 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 7.036 | |
| 2 | HDPE | 75 | 0.06 | |
| 3 | HDPE | 90 | 0.706 | |
| 4 | HDPE | 110 | 0.885 | |
| 5 | HDPE | 125 | 0.535 | |
| 6 | HDPE | 140 | 0.886 | |
| 7 | HDPE | 160 | 0.537 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 489 |