Project Completion Certificate (Ground Water)
Scheme ID: 20019697 Name of Scheme: Saftyara No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 2740 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Aug-2023 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELLS WITH SOLAR PLANT 21 / 93.36 SAFTYARA 27.810949 79.876464
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 540 / 41 SAFTYARA 27.810949 79.876464
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC STRUCTURE WITH ZINCALUME WATER TANK 150 / 12 SAFTYARA 27.810979 79.879165
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 125 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / 6Kg 63 4.330 Distribution Network
2 HDPE / 6Kg 75 0.390 Distribution Network
3 HDPE / 6Kg 90 0.093 Distribution Network
4 HDPE / 6Kg 110 0.071 Distribution Network
5 HDPE / 6Kg 140 1.010 Distribution Network
6 HDPE / 6Kg 160 1.180 Distribution Network
HSC Connection
Sno. Total Nos.
1 462
Other Details
2.39
0.00
2.38
30-Nov-2023
16-Nov-2024