| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20019697 | Name of Scheme: Saftyara | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 2740 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Aug-2023 | Actual Date of Completion (Capex): 31-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELLS WITH SOLAR PLANT | 21 / 93.36 | SAFTYARA | 27.810949 | 79.876464 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 540 / 41 | SAFTYARA | 27.810949 | 79.876464 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | RCC STRUCTURE WITH ZINCALUME WATER TANK | 150 / 12 | SAFTYARA | 27.810979 | 79.879165 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 | 125 | 0.030 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE / 6Kg | 63 | 4.330 | Distribution Network |
| 2 | HDPE / 6Kg | 75 | 0.390 | Distribution Network |
| 3 | HDPE / 6Kg | 90 | 0.093 | Distribution Network |
| 4 | HDPE / 6Kg | 110 | 0.071 | Distribution Network |
| 5 | HDPE / 6Kg | 140 | 1.010 | Distribution Network |
| 6 | HDPE / 6Kg | 160 | 1.180 | Distribution Network |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 462 |