| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20019920 | Name of Scheme: Karamchand Pur W/S Scheme | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1724 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 26-Aug-2022 | Actual Date of Completion (Capex): 10-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 200X150 MM TUBE WELL | 15.03 / 110.52 | KARAMCHANDPUR | 27.263307° | 79.49944° |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 400 CUM / 51 | KARAMCHANDPUR | 27.263307° | 79.49944° |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 100 KL / 12 M STAGING | KARAMCHANDPUR | 27.263307° | 79.49944° |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 80 | .0171 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 75 | .0451 | |
| 2 | HDPE | 90 | .1825 | |
| 3 | HDPE | 110 | .171 | |
| 4 | HDPE | 140 | .3337 | |
| 5 | HDPE | 63 | 3.0513 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 398 |