Project Completion Certificate (Ground Water)
Scheme ID: 20020253 Name of Scheme: SARSWA No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 3773 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 25-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24.45 Mtr / 108.36 Mtr SARSWA 29.136057 77.779249
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 800 LPM / 54 Mtr SARSWA 29.136057 77.779249
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225 Kl / 16 M SARSWA 29.136057 77.779249
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.0225
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.667
2 HDPE 90 2.254
3 HDPE 110 0.608
4 HDPE 125 0.205
HSC Connection
Sno. Total Nos.
1 674
Other Details
3.39
3.39
2.73
11-Feb-2025
12-Feb-2025