| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20020528 | Name of Scheme: KURWA, MAINABHAGAR, BARIARPUR | No. of Villages: 5 | No. of Habitation Covered: 6 |
| Total Population Covered: 5110 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 04-Feb-2024 | Actual Date of Completion (Capex): 05-Jul-2026 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 33/147.84 | Kurwa, Minabhagar & Bariarpur | 26.49 | 83.15 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersile Pump | 60/46 | Kurwa, Minabhagar & Bariarpur | 26.49 | 83.15 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Overhead Tnk | 300/18 | Kurwa, Minabhagar & Bariarpur | 26.49 | 83.15 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.022 | Laying Completed |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 16.57 | Laying Completed |
| 2 | HDPE | 75 | 1.22 | Laying Completed |
| 3 | HDPE | 90 | .88 | Laying Completed |
| 4 | HDPE | 110 | 1.08 | Laying Completed |
| 5 | HDPE | 140 | 0.70 | Laying Completed |
| 6 | HDPE | 160 | 1.02 | Laying Completed |
| 7 | HDPE | 200 | 1.92 | Laying Completed |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 780 |