Project Completion Certificate (Ground Water)
Scheme ID: 20020947 Name of Scheme: KULANJAN No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 6001 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 24-Jan-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 37.85 Mtr / 99.75 Mtr KULANJAN 29.151706 77.656499
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 1300 LPM / 54 Mtr KULANJAN 29.151706 77.656499
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 375 Kl / 16 M KULANJAN 29.151706 77.656499
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 200 0.0227
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.390
2 HDPE 90 1.586
3 HDPE 110 0.183
4 HDPE 125 0.165
5 HDPE 140 0.243
6 HDPE 160 0.106
HSC Connection
Sno. Total Nos.
1 1117
Other Details
4.27
4.27
3.49
11-Jun-2024
31-Dec-2024