Project Completion Certificate (Ground Water)
Scheme ID: 20021706 Name of Scheme: Babri Village Water Supply Scheme Reorgination No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 11544 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 30-Mar-2024 Actual Date of Completion (Capex): 30-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 300 mm 60 mtr plain pipe old oht campus 29.50410 77.43289
2 200 mm 36 mtr strainer old oht campus 29.50410 77.43289
3 200 mm 51 mtr plain pipe old oht campus 29.50410 77.43289
4 300 mm 60 mtr plain pipe new oht campus 29.48573 77.42706
5 200 mm 55.20 mtr plain pipe new oht campus 29.48573 77.42706
6 200 mm 41.50 mtr strainer new oht campus 29.48573 77.42706
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 40 hp 1600 lpm/ 56 mtr head new oht campus 29.48573 77.42706
2 40 hp 1600 lpm/ 56 mtr head old oht campus 29.50410 77.43289
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC structure 500 kl/ 15 mtr new oht campus 29.48573 77.42706
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K9 250 0.06
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 19.725
2 HDPE 75 2.583
3 HDPE 90 1.658
4 HDPE 110 1.938
5 HDPE 125 0.963
6 HDPE 140 0.326
7 HDPE 160 0.179
8 HDPE 200 0.062
HSC Connection
Sno. Total Nos.
1 2334
Other Details
703.76
689.59
689.59
24-Jul-2024
25-Dec-2024