| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20022060 | Name of Scheme: Roni harjipur | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 8632 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 04-Feb-2024 | Actual Date of Completion (Capex): 05-Nov-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 36.05 M /119.27 M | Roni Harjipur | 29.544078 | 77.49609 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 2200 LPM / 49 M | Roni Harjipur | 29.544078 | 77.49609 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 550 KL / 14 M | Roni Harjipur | 29.544078 | 77.49609 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I | 300 | 0.059 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 1.364 | |
| 2 | HDPE | 75 | 1.818 | |
| 3 | HDPE | 63 | 12.992 | |
| 4 | HDPE | 110 | 0.910 | |
| 5 | HDPE | 125 | 0.075 | |
| 6 | HDPE | 140 | 0.112 | |
| 7 | HDPE | 160 | 0.553 | |
| 8 | HDPE | 180 | 0.571 | |
| 9 | HDPE | 200 | 0.490 | |
| 10 | D.I | 250 | 0.273 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 1675 |