Project Completion Certificate (Ground Water)
Scheme ID: 20022134 Name of Scheme: SAGARAPUR No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 2170 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 05-Mar-2023 Actual Date of Completion (Capex): 03-Oct-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 18Mtr/ 130.8Mtr SAGARAPUR 27.409829 80.297344
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.5 M³ per Min /45Mtr SAGARAPUR 27.409829 80.297344
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150KL/ 16Mtr SAGARAPUR 27.409874 80.297324
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 150 0.020
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 1.665
2 HDPE Pipe PN-6, Class PE-100 75 1.685
3 HDPE Pipe PN-6, Class PE-100 90 2.189
4 HDPE Pipe PN-6, Class PE-100 110 0.915
5 HDPE Pipe PN-6, Class PE-100 125 0.338
6 HDPE Pipe PN-6, Class PE-100 160 0.046
HSC Connection
Sno. Total Nos.
1 400
Other Details
2.34
0.00
2.00
02-Jan-2024
25-Dec-2024