| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20022725 | Name of Scheme: Dharmangadpur | No. of Villages: 2 | No. of Habitation Covered: 7 |
| Total Population Covered: 2900 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 08-May-2023 | Actual Date of Completion (Capex): 21-Jul-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 11.05 Mtr./ 40.52 Mtr. | Dharmangadpur | 26.861838 | 79.595316 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 36 (M3/ Hr.)/ 46 Mtr. | Dharmangadpur | 26.861838 | 79.595316 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 175 Kl/ 16 Mtr. | Dharmangadpur | 26.861776 | 79.595333 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. | 150 | 0.0135 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.015 | |
| 2 | HDPE | 75 | 1.418 | |
| 3 | HDPE | 90 | 0.19 | |
| 4 | HDPE | 110 | 0.975 | |
| 5 | HDPE | 140 | 0.993 | |
| 6 | HDPE | 160 | 0.137 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 327 |