| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20023019 | Name of Scheme: BAJAUT PWS | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2395 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 25-May-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 27.39 Mtr / 94.46 Mtr | BAJAUT | 28.93241 | 77.712462 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 550 LPM / 52 Mtr | BAJAUT | 28.93241 | 77.712462 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 150 Kl / 14 M | BAJAUT | 28.93241 | 77.712462 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.0204 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 3.523 | |
| 2 | HDPE | 90 | 0.376 | |
| 3 | HDPE | 110 | 0.235 | |
| 4 | HDPE | 125 | 0.115 | |
| 5 | HDPE | 140 | 0.175 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 566 |