Project Completion Certificate (Ground Water)
Scheme ID: 20023253 Name of Scheme: Bagojhar Water Supply Scheme No. of Villages: 10 No. of Habitation Covered: 11
Total Population Covered: 12 Base Year: 2027 Intermediate Year: 2028 Design Year: 2029
Date of Completion (As per Contract): 22-Nov-2024 Actual Date of Completion (Capex): 23-Nov-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
HSC Connection
Sno. Total Nos.
Other Details
1.70
1.80
1.90
24-Nov-2024
25-Nov-2024