| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20023265 | Name of Scheme: Ramduttpur WS | No. of Villages: 4 | No. of Habitation Covered: 290 |
| Total Population Covered: 2650 | Base Year: 2022 | Intermediate Year: 2027 | Design Year: 2032 |
| Date of Completion (As per Contract): 24-Mar-2024 | Actual Date of Completion (Capex): 24-Mar-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Strainer | 21 | Ramduttpur | 25.498587 | 83.186843 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 600/14 | Ramduttpur | 25.498587 | 83.186843 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 175/14 | Ramduttpur | 25.498587 | 83.186843 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.045 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 1.119 | |
| 2 | HDPE | 75 | 4.571 | |
| 3 | HDPE | 63 | 7.58 | |
| 4 | HDPE | 110 | 0.163 | |
| 5 | HDPE | 125 | 0.439 | |
| 6 | HDPE | 140 | 0.507 | |
| 7 | HDPE | 160 | 0.082 | |
| 8 | HDPE | 180 | 0.06 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |