Project Completion Certificate (Ground Water)
Scheme ID: 20024687 Name of Scheme: UMARA JJM SCHEME No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 3987 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 22-Mar-2024 Actual Date of Completion (Capex): 21-Jan-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 23M/102.30M Umara 28.35698 80.942306
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT PUMP 850M3/39M Umara 28.35698 80.942306
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225KL/16M Umara 28.35698 80.942306
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 150 0.029
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.893
2 HDPE 75 0.298
3 HDPE 90 1.071
4 HDPE 110 1.440
5 HDPE 140 0.291
6 HDPE 160 0.401
7 HDPE 200 0.127
HSC Connection
Sno. Total Nos.
1 596
Other Details
2.35
0.00
2.35
21-Oct-2024
21-Jan-2025