Project Completion Certificate (Ground Water)
Scheme ID: 20025196 Name of Scheme: Kudauli Madauli No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 3086 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Sep-2023 Actual Date of Completion (Capex): 05-Dec-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 30.29/174.34 KUDAULI MADAULI 26.507512 79.651757
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 700/62 KUDAULI MADAULI 26.507512 79.651757
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200/16 KUDAULI MADAULI 26.507512 79.651757
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI/K7 150 0.1340
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.400
2 HDPE 90 1.854
3 HDPE 110 1.286
4 HDPE 125 143.7
5 HDPE 140 0.383
6 HDPE 160 0.150
HSC Connection
Sno. Total Nos.
1 488
Other Details
3.13
0.00
2.55
19-Mar-2024
20-Mar-2024