Project Completion Certificate (Ground Water)
Scheme ID: 20025228 Name of Scheme: Salaiya PWS No. of Villages: 3 No. of Habitation Covered: 2
Total Population Covered: 3510 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Sep-2022 Actual Date of Completion (Capex): 25-Sep-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.173
2 HDPE 90 2.312
3 HDPE 110 1.688
4 HDPE 125 .763
5 HDPE 140 .356
HSC Connection
Sno. Total Nos.
Other Details
2.67
0.00
2.65
08-Jun-2023
01-Nov-2024