Project Completion Certificate (Ground Water)
Scheme ID: 20025503 Name of Scheme: Karom No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 2400 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 24-Aug-2022 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.965 Actuals
2 HDPE 75 1.025 Actuals
3 HDPE 90 0.973 Actuals
4 HDPE 110 0.840 Actuals
5 HDPE 140 0.527 Actuals
6 HDPE 160 0.107 Actuals
HSC Connection
Sno. Total Nos.
Other Details
1.59
1.73
1.73
07-Nov-2023
01-Dec-2023