| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20025932 | Name of Scheme: Nagari PWS | No. of Villages: 1 | No. of Habitation Covered: 3 |
| Total Population Covered: 1470 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 22-Sep-2023 | Actual Date of Completion (Capex): 16-Mar-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBE WELL | 12.10 MTR/130.40 MTR | NAGARI | 26.940542 | 78.824386 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUMERSIBLE | 21 M^3 /53 MTR | NAGARI | 26.940542 | 78.824386 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 100 KL/ 12 MTR | NAGARI | 26.940542 | 78.824386 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.040 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 1.105 | |
| 2 | HDPE | 75 | 0.319 | |
| 3 | HDPE | 90 | 0.560 | |
| 4 | HDPE | 110 | .575 | |
| 5 | HDPE | 140 | .700 | |
| 6 | HDPE | 160 | .779 | |
| 7 | HDPE | 180 | .461 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 266 |