Project Completion Certificate (Ground Water)
Scheme ID: 20026176 Name of Scheme: Budhpur Nainsingh Village Water Supply No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2899 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 18-Aug-2024 Actual Date of Completion (Capex): 18-Apr-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 18.02/129.28 Bundpur Nain singh 78.195578 29.476006
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submerssible Pump 10 HP 500 /44 Bundpur Nain singh 78.195578 29.476006
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/14 Bundpur Nain singh 78.195578 29.476006
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D I K-7 Pipe 125 40
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6 , PE-100 63 4.091
2 HDPE Pipe PN-6 , PE-100 75 0.103
3 HDPE Pipe PN-6 , PE-100 110 1.704
4 HDPE Pipe PN-6 , PE-100 140 0.648
5 HDPE Pipe PN-6 , PE-100 160 0.199
HSC Connection
Sno. Total Nos.
1 447
Other Details
1.84
1.84
1.84
24-Jul-2024
25-Jul-2024