Project Completion Certificate (Ground Water)
Scheme ID: 20026407 Name of Scheme: Samaspur PWS No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 3935 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 15-Apr-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 29 Mtr/ 136.32 Mtr Samaspur 26.727452* 79.182387*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 51 M^3 /46 Mtr Samaspur 26.727452* 79.182387*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 250 KL / 16 Mtr Samaspur 26.727452* 79.182387*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.0195
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.936
2 HDPE 75 1.817
3 HDPE 90 .745
4 HDPE 110 1.216
5 HDPE 140 .443
6 HDPE 160 .751
7 HDPE 180 .557
HSC Connection
Sno. Total Nos.
1 734
Other Details
2.07
2.80
2.80
15-Apr-2024
16-Apr-2024