Project Completion Certificate (Ground Water)
Scheme ID: 20026426 Name of Scheme: Chandpura PWS No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 3339 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 21-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBE WELL 24.02 MTR/119.85 MTR CHANDPURA 26.6843.95 79.103161
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 42 M^3/ 49 MTR CHANDPURA 26.6843.95 79.103161
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200 KL /16 MTR CHANDPURA 26.684395 79.103161
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 125 0.054
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.021
2 HDPE 75 0.407
3 HDPE 90 0.300
4 HDPE 110 0.725
5 HDPE 180 0.874
6 HDPE 140 0.089
HSC Connection
Sno. Total Nos.
1 670
Other Details
1.77
2.54
2.54
23-Dec-2024
24-Dec-2024