| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20026590 | Name of Scheme: PAHLI KUTUBPUR | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 1530 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 29-Mar-2024 | Actual Date of Completion (Capex): 20-Jun-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 150X200 MM TUBEWELL | 153.01 | PARMI KUTUBPUR | 25.902605 | 80.93574 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | 10 HP | 350/55 | PARMI KUTUBPUR | 25.902605 | 80.93574 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVER HEAD TANK | 100/12 | PARMI KUTUBPUR | 25.902598 | 80.935728 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI PIPE 80 MM K-9 | 80 | 0.03 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE | 160 | 118 | |
| 2 | HDPE PIPE | 125 | 122 | |
| 3 | HDPE PIPE | 110 | 230 | |
| 4 | HDPE PIPE | 90 | 404 | |
| 5 | HDPE PIPE | 75 | 706 | |
| 6 | HDPE PIPE | 63 | 1152 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 314 |