| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20029767 | Name of Scheme: Bewada WS | No. of Villages: 2 | No. of Habitation Covered: 389 |
| Total Population Covered: 2450 | Base Year: 2022 | Intermediate Year: 2027 | Design Year: 2032 |
| Date of Completion (As per Contract): 17-Dec-2024 | Actual Date of Completion (Capex): 17-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Strainer | 24 | Bewada WS | 25.434694 | 83.412824 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 550/14 | Bewada WS | 25.434694 | 83.412824 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | service reservoir | 150/14 | Bewada WS | 25.434694 | 83.412824 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.03 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 0.741 | |
| 2 | HDPE | 75 | 2.091 | |
| 3 | HDPE | 63 | 5.548 | |
| 4 | HDPE | 110 | 1.49 | |
| 5 | HDPE | 125 | 1.043 | |
| 6 | HDPE | 140 | 0.447 | |
| 7 | HDPE | 160 | 0.4458 | |
| 8 | HDPE | 180 | 0.023 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 389 |