Project Completion Certificate (Ground Water)
Scheme ID: 20030159 Name of Scheme: HALIM NAGAR GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 5140 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 12-Oct-2023 Actual Date of Completion (Capex): 30-Oct-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 30.00/90.42 Halim Nagar 26.804411 81.753848
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump 1070 LPM / 40 Mtr Halim Nagar 26.804411 81.753848
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 300/14 Halim Nagar 26.80443 81.754029
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 0.0109
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE - 100 200 0.0538
2 HDPE Pipe PN-6: Class PE - 100 180 0.9501
3 HDPE Pipe PN-6: Class PE - 100 160 1.0234
4 HDPE Pipe PN-6: Class PE - 100 140 0.1998
5 HDPE Pipe PN-6: Class PE - 100 125 0.4218
6 HDPE Pipe PN-6: Class PE - 100 110 0.7543
7 HDPE Pipe PN-6: Class PE - 100 90 1.4047
8 HDPE Pipe PN-6: Class PE - 100 75 1.9463
9 HDPE Pipe PN-6: Class PE - 100 63 9.3933
HSC Connection
Sno. Total Nos.
1 914
Other Details
3.51
0.00
4.24
30-Oct-2023
15-Nov-2024