| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20030546 | Name of Scheme: MINAPUR FAGAULI & FAGOLI KUARMIYAN GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME | No. of Villages: 4 | No. of Habitation Covered: 7 |
| Total Population Covered: 6690 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 12-Oct-2023 | Actual Date of Completion (Capex): 24-Nov-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 29.85/94.15 | MINAPUR FAGOLI | 26.80099 | 81.74503 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT PUMP | 1330LPM/45Mtr | MINAPUR FAGOLI | 26.80099 | 81.74503 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 400/16 | MINAPUR FAGOLI | 26.80099 | 81.74503 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 150 | 0.038 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6: Class PE-100 | 200 | 1.4523 | |
| 2 | HDPE Pipe PN-6: Class PE-100 | 180 | 1.0029 | |
| 3 | HDPE Pipe PN-6: Class PE-100 | 160 | 0.5917 | |
| 4 | HDPE Pipe PN-6: Class PE-100 | 140 | 0.5634 | |
| 5 | HDPE Pipe PN-6: Class PE-100 | 125 | 1.0276 | |
| 6 | HDPE Pipe PN-6: Class PE-100 | 110 | 0.8043 | |
| 7 | HDPE Pipe PN-6: Class PE-100 | 90 | 0.5619 | |
| 8 | HDPE Pipe PN-6: Class PE-100 | 75 | 1.3247 | |
| 9 | HDPE Pipe PN-6: Class PE-100 | 63 | 15.5323 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 974 |