Project Completion Certificate (Ground Water)
Scheme ID: 20031490 Name of Scheme: BIHARA GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 6
Total Population Covered: 4020 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 12-Oct-2023 Actual Date of Completion (Capex): 30-Nov-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 24.00 / 126.30 Bihara 26.611251 81.70416
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT PUMP 850LPM / 46Mtr Bihara 26.611251 81.70416
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 oht 250/14 Bihara 26.611264 81.703981
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 125 0.0248
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 200 0.0000
2 HDPE Pipe PN-6: Class PE-100 180 0.0000
3 HDPE Pipe PN-6: Class PE-100 160 0.3591
4 HDPE Pipe PN-6: Class PE-100 140 1.7295
5 HDPE Pipe PN-6: Class PE-100 125 0.0000
6 HDPE Pipe PN-6: Class PE-100 110 0.5072
7 HDPE Pipe PN-6: Class PE-100 90 3.3343
8 HDPE Pipe PN-6: Class PE-100 75 1.0348
9 HDPE Pipe PN-6: Class PE-100 63 14.3742
HSC Connection
Sno. Total Nos.
1 845
Other Details
3.28
0.00
3.95
30-Nov-2023
01-Feb-2025