Project Completion Certificate (Ground Water)
Scheme ID: 20031497 Name of Scheme: DILWAL GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 4
Total Population Covered: 3550 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 12-Oct-2023 Actual Date of Completion (Capex): 12-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 24.00/107.50 DILWAL 26.767027 81.64938
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT PUMP 690LPM/48Mtr DILWAL 26.767027 81.64938
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200/16 DILWAL 26.767027 81.64938
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 125 0.0105
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 200 0.0000
2 HDPE Pipe PN-6: Class PE-100 180 0.0000
3 HDPE Pipe PN-6: Class PE-100 160 0.7236
4 HDPE Pipe PN-6: Class PE-100 140 0.5313
5 HDPE Pipe PN-6: Class PE-100 125 0.0000
6 HDPE Pipe PN-6: Class PE-100 110 0.1491
7 HDPE Pipe PN-6: Class PE-100 90 1.8350
8 HDPE Pipe PN-6: Class PE-100 75 0.2743
9 HDPE Pipe PN-6: Class PE-100 63 9.6533
HSC Connection
Sno. Total Nos.
1 605
Other Details
2.74
0.00
3.30
12-Mar-2024
30-Nov-2024