Project Completion Certificate (Ground Water)
Scheme ID: 20031858 Name of Scheme: DHINDALA No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2917 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 12-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 27.65 Mtr / 100.85 Mtr DHINDALA 28.922767 77.588615
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 600 LPM / 50 Mtr DHINDALA 28.922767 77.588615
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175 Kl / 14 M DHINDALA 28.922767 77.588615
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.022
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.656
2 HDPE 90 0.927
3 HDPE 110 0.330
4 HDPE 125 0.192
5 HDPE 140 0.442
HSC Connection
Sno. Total Nos.
1 568
Other Details
2.64
2.64
2.14
29-Jul-2024
07-Oct-2024