Project Completion Certificate (Ground Water)
Scheme ID: 20033764 Name of Scheme: Faizullapur PWS No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2200 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 25-Jul-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 18.09 Mtr./77.51Mtr. Faizullahpur 26.866209* 79.431152*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 27(M3/Hr.)/42Mtr. Faizullahpur 26.866209* 79.431152*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/12 Faizullahpur 26.866215* 79.431343*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 34.20
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7491.00
2 HDPE 75 1401.00
3 HDPE 90 299.10
4 HDPE 110 282.00
5 HDPE 125 941.50
6 HDPE 140 862.5
7 HDPE 160 103.00
HSC Connection
Sno. Total Nos.
1 391
Other Details
1.59
1.92
1.92
16-Nov-2023
17-Nov-2023