Project Completion Certificate (Ground Water)
Scheme ID: 20033821 Name of Scheme: NASRULLAPUR WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 3190 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 21-Oct-2023 Actual Date of Completion (Capex): 24-Jan-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering of Tubewell Assembly 30.05/110.74 Nasrullahpur 26.54829384 82.546950006
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Ac Submersible Pump 15 hp 0.7/48 Nasrullahpur 26.54829384 82.546950006
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC 200KL/16 Nasrullahpur 26.5423962 82.5495236
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 200 0.021
2 DI-K7 150 0.016
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 1.150
2 HDPE Pipe PN-6: Class PE-100 75 0.564
3 HDPE Pipe PN-6: Class PE-100 63 12.936
4 HDPE Pipe PN-6: Class PE-100 110 0.634
5 HDPE Pipe PN-6: Class PE-100 125 0.780
6 HDPE Pipe PN-6: Class PE-100 140 0.0278
7 HDPE Pipe PN-6: Class PE-100 160 1.181
8 HDPE Pipe PN-6: Class PE-100 200 0.0258
HSC Connection
Sno. Total Nos.
1 580
Other Details
2.52
2.52
2.54
24-Apr-2025
25-Apr-2025