Project Completion Certificate (Ground Water)
Scheme ID: 20034277 Name of Scheme: BAIRI DARIYON No. of Villages: 1 No. of Habitation Covered: 4
Total Population Covered: 3170 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 24-Nov-2022 Actual Date of Completion (Capex): 23-Nov-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.84
2 HDPE 75 2.367
3 HDPE 90 1.51
4 HDPE 110 0.501
5 HDPE 125 1.147
6 HDPE 140 0.788
7 HDPE 160 0.161
HSC Connection
Sno. Total Nos.
Other Details
2.22
2.40
2.40
31-Mar-2023
01-Apr-2023