Project Completion Certificate (Ground Water)
Scheme ID: 20034281 Name of Scheme: GOPALPUR TALUKA No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2270 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 23-Nov-2023 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.528 Actuals
2 HDPE 75 1.406 Actuals
3 HDPE 90 0.759 Actuals
4 HDPE 110 1.096 Actuals
5 HDPE 125 1.031 Actuals
6 HDPE 160 0.796 Actuals
HSC Connection
Sno. Total Nos.
Other Details
1.90
1.99
1.99
28-Feb-2024
01-Mar-2024