| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20034560 | Name of Scheme: CHHACHHARAULI WSS | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2450 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 06-Aug-2025 | Actual Date of Completion (Capex): 16-Feb-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | DC/RC Drilling including Hiring Transportaion , Erection , Dismantling with Loading and unloading of Rig and assosiated T&P complete in all respect including required all material labour & T&P etc. | 27.02/120.12 | Chhachrauli | 29.751977 | 77.379058 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | AC Submersible Pumping plant | 500/50 | Chhachrauli | 29.751977 | 77.379058 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Construction of Zinc Alum Over Head Tank | 150/12 | Chhachrauli | 29.751876 | 77.378994 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | Ductile Iron K-7 | 100 | .030 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipes | 160 | 4.662 | 63mm to 160 mm |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 411 |