Project Completion Certificate (Ground Water)
Scheme ID: 20035487 Name of Scheme: Chormara Kamalpur No. of Villages: 6 No. of Habitation Covered: 12
Total Population Covered: 4442 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 17-Feb-2024 Actual Date of Completion (Capex): 22-Apr-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 28.2 / 36.82 Chormara Kamalpur 26.41295979 82.37835917
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump -1 950 LPM Chormara Kamalpur 26.41295979 82.37835917
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 250 KL / 16 mtr Chormara Kamalpur 26.41295979 82.37835917
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 200 18
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 63 16.753
2 HDPE PN-6 75 0.598
3 HDPE PN-6 90 1.75
4 HDPE PN-6 110 3.544
5 HDPE PN-6 140 1.33
6 HDPE PN-6 160 2.82
7 HDPE PN-6 200 0.08
HSC Connection
Sno. Total Nos.
1 641
Other Details
3.18
3.76
3.70
09-Feb-2025
26-Feb-2025