Project Completion Certificate (Ground Water)
Scheme ID: 20035943 Name of Scheme: SANDA KHURD WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2650 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 30-Oct-2023 Actual Date of Completion (Capex): 02-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 MSERW Plain Pipe DIA-200MM 36.77 SANDA KHURD 27.203752 83.76057
2 MSERW Plain Pipe DIA-150MM 27 SANDA KHURD 27.203752 83.76057
3 MSERW SLOTTED PIPE DIA-150MM 16 SANDA KHURD 27.203752 83.76057
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 35.99/37 SANDA KHURD 27.203752 83.76057
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 ZINK-ALM OHT TANK 175KL/12Mtr. SANDA KHURD 27.203518 83.760422
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DOUBLE FLANGED PIPE/DI 150 0.0192
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 PN-6,PE-100/HDPE 63 1.285
2 PN-6,PE-100/HDPE 75 0.672
3 PN-6,PE-100/HDPE 90 0.656
4 PN-6,PE-100/HDPE 110 0.66
5 PN-6,PE-100/HDPE 125 0.476
6 PN-6,PE-100/HDPE 140 0.122
HSC Connection
Sno. Total Nos.
1 334
Other Details
1.96
1.96
1.96
01-Mar-2025
02-Mar-2025