Project Completion Certificate (Ground Water)
Scheme ID: 20036895 Name of Scheme: KHOZI PUR GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 4
Total Population Covered: 5767 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 14-Nov-2024 Actual Date of Completion (Capex): 07-Apr-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 26.20/119.13 KHOZI PUR 79.504659 27.106948
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump-1 1150 LPM/61 M KHOZI PUR 79.504659 27.106948
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 325 KL/ 14 M KHOZI PUR 79.504659 27.106948
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.0015 Rising main
2 DI 150 0.018 Rising main
3 DI 200 0.006 Rising main
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 1.29 Distribution
2 HDPE 63 11.48 Distribution
3 HDPE 110 1.002 Distribution
4 HDPE 140 2.50 Distribution
5 HDPE 160 0.71 Distribution
HSC Connection
Sno. Total Nos.
1 1045
Other Details
4.73
4.64
4.73
11-Jul-2024
12-Jul-2024