Project Completion Certificate (Ground Water)
Scheme ID: 20037269 Name of Scheme: SHAHPUR ZADID No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2710 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 22-Feb-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24.16 M / 94.09 M Shahpur Zadid 29°09'50.3"N 77°44'39.0"E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 600 LPM / 50 M Shahpur Zadid 29°09'50.3"N 77°44'39.0"E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 175 Kl / 14 M Shahpur Zadid 29°09'50.3"N 77°44'39.0"E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 100 0.019
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.069
2 HDPE 90 1.149
3 HDPE 110 1.034
4 HDPE 125 0.427
5 HDPE 140 0.323
HSC Connection
Sno. Total Nos.
1 524
Other Details
2.80
2.80
2.25
30-Apr-2024
09-Nov-2024