Project Completion Certificate (Ground Water)
Scheme ID: 20048086 Name of Scheme: SAGARTHALI AND CHAUPURA MOLVI MULTI VILLAGE WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 1972 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 02-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Solar Powered Pump 18.06/96.5 Sagarthali 28.5243 78.1335
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Solar Powered Pump 400/43 Sagarthali 28.5243 78.1335
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Cast in situ Zinc Zincalume 125/12 Sagarthali 28.5244 78.13357
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7/DI 100 0.025 Installed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 PN-6 PE100/HDPE 63 5.78750
2 PN-6 PE100/HDPE 75 0.2154
3 PN-6 PE100/HDPE 90 0.3626
4 PN-6 PE100/HDPE 125 0.2093
5 PN-6 PE100/HDPE 140 0.082
HSC Connection
Sno. Total Nos.
1 368
Other Details
1.55
0.00
1.55
16-Jul-2025
17-Jul-2025