Project Completion Certificate (Ground Water)
Scheme ID: 20050551 Name of Scheme: KHETATA WSS No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2860 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 16-Jun-2024 Actual Date of Completion (Capex): 11-Aug-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24.02 Mtr/ 97.55 M Khetata 28.473121 78.846301
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 10 HP Submersible Pump 36 cum / 46 M Khetata 28.473121 78.846301
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Conventional OHT 175 KL/ 14 M Khetata 28.473121 78.846301
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 125 0.027 k7
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 0.1939
2 HDPE Pipe PN-6: Class PE-100 75 0.1735
3 HDPE Pipe PN-6: Class PE-100 63 4.252
4 HDPE Pipe PN-6: Class PE-100 110 0.2663
5 HDPE Pipe PN-6: Class PE-100 140 1.3908
6 HDPE Pipe PN-6: Class PE-100 200 0.065
HSC Connection
Sno. Total Nos.
1 500
Other Details
1.98
1.96
1.96
10-Nov-2024
11-Nov-2024