Project Completion Certificate (Ground Water)
Scheme ID: 20050630 Name of Scheme: CHANDAUKI WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 9
Total Population Covered: 3250 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 04-May-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 MS Pipes 24.8 m / 248.98 m Chandauki 25.70379 82.19608
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 H.P Submmercible Pump 640 /43 Chandauki 25.70379 82.19608
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank 175 KL 12 M Staging Chandauki 25.70364 82.19629
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 0.02596
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 1.129
2 HDPE Pipe PN-6: Class PE-100 75 3.012
3 HDPE Pipe PN-6: Class PE-100 110 0.619
4 HDPE Pipe PN-6: Class PE-100 125 0.430
5 HDPE Pipe PN-6: Class PE-100 160 0.597
6 HDPE Pipe PN-6: Class PE-100 180 0.528
7 HDPE Pipe PN-6: Class PE-100 200 0.022
8 HDPE Pipe PN-6: Class PE-100 63 11.392
HSC Connection
Sno. Total Nos.
1 548
Other Details
2.22
2.11
2.11
10-Mar-2025
11-Mar-2025