| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20052334 | Name of Scheme: Taiyapur &Amohar water supply scheme | No. of Villages: 1 | No. of Habitation Covered: 4 |
| Total Population Covered: 4716 | Base Year: 2023 | Intermediate Year: 0 | Design Year: 0 |
| Date of Completion (As per Contract): 01-Jun-2022 | Actual Date of Completion (Capex): 06-Nov-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBE WELL | 24.11 / 73.23 | TAIYAPUR | 26.65093 | 79.602441 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 950 LMP / 49M | TAIYAPUR | 26.65093 | 79.602441 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 275 / 12 | TAIYAPUR | 26.65093 | 79.602441 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.0134 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.819 | |
| 2 | HDPE | 90 | 3.1384 | |
| 3 | HDPE | 110 | 0.267 | |
| 4 | HDPE | 160 | 1.434 | |
| 5 | HDPE | 180 | 2.160 | |
| 6 | HDPE | 125 | 1.111 | |
| 7 | HDPE | 140 | 0.0125 | |
| 8 | HDPE | 200 | 0.581 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 754 |