| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20053094 | Name of Scheme: Kaprahat | No. of Villages: 1 | No. of Habitation Covered: 4 |
| Total Population Covered: 4703 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 18-Nov-2023 | Actual Date of Completion (Capex): 15-Dec-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 1 | 33.17/217.24 | KAPRAHAT | 26.59393 | 79.89358 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | JASCO | 1000/64 | KAPRAHAT | 26.59393 | 79.89358 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 275/18 | KAPRAHAT | 26.59393 | 79.89358 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI/K7 | 150 | 0.0137 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 7.857 | |
| 2 | HDPE | 90 | 2.406 | |
| 3 | HDPE | 110 | 1.983 | |
| 4 | HDPE | 125 | 1091 | |
| 5 | HDPE | 140 | 0.702 | |
| 6 | HDPE | 160 | 1.080 | |
| 7 | HDPE | 180 | 0.671 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |