Project Completion Certificate (Ground Water)
Scheme ID: 20053242 Name of Scheme: Kasmara No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 2964 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 18-Nov-2023 Actual Date of Completion (Capex): 27-Dec-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 9/94.91 KASMARA 26.745922 79.857164
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 650/64 KASMARA 26.745922 79.857164
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175/18 KASMARA 26.745922 79.857164
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI/K7 100 0.0148
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.295
2 HDPE 90 1.886
3 HDPE 110 2.659
4 HDPE 125 0.202
5 HDPE 160 0.124
6 HDPE 180 0.725
HSC Connection
Sno. Total Nos.
1 538
Other Details
3.27
0.00
2.68
11-May-2024
12-May-2024