Project Completion Certificate (Ground Water)
Scheme ID: 20056125 Name of Scheme: Nandgaon PWS No. of Villages: 3 No. of Habitation Covered: 8
Total Population Covered: 1890 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 10-Oct-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBE WELL 24.0Mtr./153.50Mtr. NANDGAON 26.420699 79.522447
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE (28.0 M3/Hr.)/53Mtr. NANDGAON 26.420699 79.522447
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150/16 NANDGAON 26.420993 79.522495
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 100 .026
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.40
2 HDPE 75 3.03
3 HDPE 110 1.43
4 HDPE 140 1.47
HSC Connection
Sno. Total Nos.
1 366
Other Details
1.65
2.14
2.14
31-Jan-2024
01-Feb-2024