Project Completion Certificate (Ground Water)
Scheme ID: 20056126 Name of Scheme: Nasirabad No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 3200 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Sep-2023 Actual Date of Completion (Capex): 01-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 24.05 Mtr./109.44 Mtr. Nasirabad 26.50581988 79.47840266
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible (41.5 M3/Hr.)/53Mtr. Nasirabad 26.50581988 79.47840266
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200/16 Nasirabad 26.505576 79.478411
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 150 .015
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.22
2 HDPE 75 .37
3 HDPE 90 .081
4 HDPE 110 .15
5 HDPE 140 .88
6 HDPE 180 .15
HSC Connection
Sno. Total Nos.
1 650
Other Details
2.54
2.15
2.15
15-Jul-2024
16-Jul-2024